Test Adjust Balance

Understanding the Basics of Test, Adjust, and Balance for Engineers

A good TAB specification gets a good balance. A vague one gets a minimum effort and a report that shows little. This guide covers what engineers should specify and what the design must provide for the balancer to do the job.

What to specify

ItemWhat to write
Certifying body and standardNEBB, AABC or TABB, and the procedural standard to follow
IndependenceThe TAB firm reports to the owner or engineer and is separate from the installing contractor
ToleranceThe accepted deviation from design airflow, stated by system type
InstrumentsCalibrated, with certificates available
ScopeAir-side systems, water-side systems and any special spaces
ReportFormat, content and delivery date relative to substantial completion
DeficienciesProcess for reporting, fixing and rechecking

For what certification means in practice, see our certification guide.

What the design must provide

  • Design airflow and flow rate for every outlet, terminal and coil.
  • Balancing dampers on branches and balancing valves on water branches.
  • Test ports and access doors at the points that will be measured.
  • Straight duct sections where traverses are needed.
  • Terminal schedules with minimum and maximum airflow.
  • Control sequences the balancer can verify.

The process the specification should support

  1. The balancer reviews the drawings and raises concerns early.
  2. The contractor completes and starts systems.
  3. A pre-TAB walk confirms readiness.
  4. The balancer measures, adjusts and records.
  5. Deficiencies are reported, repaired and rechecked.
  6. The engineer reviews the report against the design.

Reading the report

Check that every outlet appears, with design and measured values. Look at the total airflow at each fan, the outdoor air quantity, the static pressures and the fan data. Read the deficiency list and check that each item has an owner. See the essential components of a report and how to read the graphs.

Common mistakes

  • Naming a body but not a procedure. The standard is what defines the work.
  • Leaving out access. A damper behind a fixed ceiling cannot be balanced.
  • Not reviewing the report. It contains the first data on how the design performs.

Questions engineers ask about TAB specifications

What tolerance should I specify?

Follow the standard you name and the needs of the project. A common figure is about 10 percent of design airflow, but critical spaces may need tighter limits.

Should the TAB firm be independent?

Many specifications require it, which gives the owner a neutral record.

When should the balancer be hired?

Early enough to review the design for provisions and to hold a date in the schedule.

A sample specification paragraph

Adapt this to your project and your standards. “The testing, adjusting and balancing contractor shall be certified by NEBB, AABC or TABB and shall perform the work in accordance with the certifying body’s procedural standards. The firm shall be independent of the installing contractors. Airflow shall be adjusted to within the stated tolerance of design, with instruments calibrated within the interval stated by the manufacturer. The final report shall include measured and design values for each outlet, fan data, static pressures, outdoor air quantities and a list of deficiencies, and shall be submitted within the stated period after testing.”

Related reading: Top HVAC Challenges Faced by Engineers During Project Design.

To discuss a TAB specification, call Ghazi Hussain at (908) 323-9780.

Need Help?

Ghazi-Hussain-Air-Balance-Masters